Case Histories - Stonebury Limited

Client: Stonebury Limited/Yorkshire Water
Service: Engineering
Project: Penstock replacement, underground service reservoir, Yorkshire

     

News

 
Achilles UVDB Verify
Adaptor for CIPP
Rope access with IRATA
Close fit liner solved
AMEX-10 Vario
 
 
A remotely operated cast iron penstock was found to be inoperable at Moseley underground reservoir in Yorkshire. PMP was commissioned to remove the old penstock and fit a new stainless steel penstock and replace the remotely controlled operating gear.

The work had to be carried out in a designated confined space in the underground reservoir. The old penstock and remote operating gear was removed and the new system was installed and tested in a two day window.