We were commissioned to survey and inspect two gate valves at Denton Water Treatment Works in Manchester to see if they were suitable for automation.

The project required the disassembly of the existing headstocks and inspection for damage. We installed lifting gear to remove the valve headstock covers. The diameter and pitch of the drive worm was measured to calculate the torque requirements of the new motor for the electric actuator.

A detailed report about the condition of the gate valves and the necessary specification for the electric actuators was submitted to the client.

Actuators were then ordered, and were fitted by PMP at a later date.