The
reservoir inlet from the hill side had become scaled up with
moss and other debris which affected the measurement of flows into
the reservoir. The monitoring station also needed to be refurbished.
PMP cleaned off all the moss and debris from the inlet walls and
base and applied a smooth cementitious coating to the surfaces.
The monitoring station was refurbished, with works being carried
out to the interior and exterior of the building and adjacent paths.