When United Utilities refurbished their Water Treatment Works at Lamaload, near Macclesfield, PMP were appointed to remove 14 pressure filters from the site.

The works were particularly difficult due to size and weight of the filters, restricted access and that sensitive electronic control panels were situated nearby.