When United Utilities refurbished
their Water Treatment Works at Lamaload, near Macclesfield, PMP
were appointed to remove 14 pressure filters from the site.
The works were particularly difficult due to size and weight of
the filters, restricted access and that sensitive electronic control
panels were situated nearby.
We carried out the works using strict measures to contain or eliminate
dust, noise and vibration.